What is the Effect of WIP on Process Cycle Times?

I hear people talking about ā€œWIPā€ and I have to say that I have no Idea what they are talking about.Ā Ā Also, I hear this ā€œWIP thingā€ used when they want to reduce the time it takes to do parts in a manufacturing plant.Ā Ā What are they talking about, and how can this help me speed up my game by improving customer delivery times?Ā Ā We are in danger of losing some customers if we don’t improve our ā€œon timeā€ customer deliveries; and this could be catastrophic in today’s economy.Ā Ā Further, we are trying desperately to maintain a credible business reputation, but we can’t seem to be able to predict and/or control our process times in manufacturing and the office.Ā Ā Our team (10 people) holds a daily morning meeting (usually 45 minutes long) to uncover some of the root causes and make changes, but we are still delivering ā€œlateā€ and our Sales people are continually apologizing and offering concessions to make up for our poor and inconsistent performance.Ā Ā Lately, my entire day is filled with fire fighting related to delivery and ā€œon timeā€ performance issues.Ā Ā Please help!

Lean Champion’s Answer:

I feel your pain!Ā Ā Let’s see if I can help.

WIP is known as ā€œWork in Processā€.Ā Ā WIP is the inventory between the start and end points of a product routing.Ā Ā ItĀ doesĀ notĀ include work in stock points.Ā Ā WIP can apply to manufacturing or other processes (such as an office process).Ā Ā In other words WIP is ā€œstuffā€ being worked on that is not in a ā€œstocked situationā€.Ā Ā WIP is an important parameter because it affects the time it takes to process parts through the system and critically affects ability to maintain quoted lead times.Ā Ā A law known as ā€œLittle’s Lawā€ pretty much tells the story.Ā Ā Little’s LawĀ is:Ā Ā Cycle Time (CT) is equal to the WIP devided byĀ Throughput (TH).Ā Ā Cycle time (CT) is the process time while the product is in WIP.Ā Ā Throughput (TH) is the inverse of cycle time.Ā Ā For Example, if a process takes 0.02 hours per part, then the throughput is:

(1 part)/(0.02 hours ) = 50 parts per hour through that process

Let’s say you have 500 parts in process (WIP) and your process is capable of doing the above 50 parts per hour (TH).Ā Ā By Little’s Law we can predict that this process will take:

(500 Parts WIP)/(50 Parts per hour TH) = 10 hours (for 500 parts)

Note: cycle time and throughput are on a ā€œtime basisā€ of hours; units must be constant for the formula to work correctly.Ā Ā You can work in minutes or days or any other time unit as long as you are consistent throughout the formula.

Now you can see that your factory is loaded for the next 10 working hours and if part sequence number 501Ā comes in you can tell the customer it will take 10 hours (queue time) + .02 hrs. (part process time), or, 10.02 working hours to produce at your present rate of 50 parts per hour with 500 parts ahead of it.Ā Ā (Don’t forget to add non-work times for ā€œcalendar timeā€ estimates).Ā Ā The 10 hours (queue time) will cause new orders to wait unless something is done to increase the throughput or invoke ā€œpassingā€ (where part sequence no. 501 jumps ahead of all or part of the preceding 500 piece order).Ā Ā The problem with passing is that it can make other orders late.Ā Ā If 10.02 working hours is unacceptable to the customer, then you will have to pull a ā€œcapacity triggerā€ (assuming ā€œpassingā€ is not acceptable) in order to shorten the 10.02 hours to an acceptable level.Ā Ā Capacity triggers increase throughput, and consequently reduce overall cycle time, to produce the parts in queue for a given amount of WIP.

Little’s law is physical law, and will prevail over the long run, so it helps us plan and improve our work; however, if we ignore it, the results can be very disappointing.Ā Ā If WIPĀ increasesĀ without adjusting throughput, our cycle times can easily go beyond acceptable limits.Ā Ā The key is knowing ā€œreal timeā€ when this is happening so you can react (without over reacting by spending too much money).Ā Ā Conversely, if WIP is reducedĀ belowĀ ā€œcritical levelsā€, throughput, and thus revenue, can decline.Ā Ā ā€œCritical WIPā€ is the WIP level where cycle time is minimum and throughput is maximum.Ā Ā Indeed, this is a delicate balance, but with the right metrics and ā€œon the floorā€ visuals this is certainly possible (even in mixed model and custom environments).Ā Using these principles, I was able to help a company drop total cycle time from 67.88 hours to 11.30 hours- an 83.3% improvement (six times faster than the original time).Ā Ā Always remember; you can’t improve what you don’t measure, nor can you manage something unless you have a way to measure it.

 

Jim McCarthy is President and Owner ofĀ Product Ventures, Inc.,Ā a consulting company for ā€œWorld Classā€ office & manufacturing improvement located in Eden Prairie, Minnesota. Certified: Lean Master. 6 Sigma Master Black Belt, Lean Leader, Lean/Six Sigma Practitioner, Lean Office Practitioner, Quick Response Manufacturing(QRM) Implementer and High Performance Leader